Install of 2 x sets of OPF Access Controller’s cabins and support equipment Tawke well drilling sites T12W.
- Prepare the ground at the designated elevation to enable the setting of the 2 sets of cabins.
- To cover the area prepared for the cabins with 2cm crushed gravel.
- block work, supply, and install concrete block under the cabin.
- septic tank pit excavation (2*2*2.5 m).
- Supplying and installing an electric water pump drawing with 1 horsepower capacity and connecting it with the main source of water and extending a wire with a socket for the electric pump and all other necessary wires that are needed. The price includes placing the electric pump in a plate box resistant to weather conditions which is to be dyed with a basic and oil-based paint.
- Provide and install the concrete foundation for lightning poles & installation
- Provide and Install Concrete Foundation for Lighting Poles, install lighting poles
- connect each cabin to the distribution electrical board using cable (4*4 mm^2), underground cable 50cm, and backfill with appropriate soil
- install spotlights and connect between the distribution of electrical board and spotlights using cable (4*4 mm^2), underground cable 50cm, and backfill with appropriate soil.
- supply material PVC pipe 4″ and all accessories and connect between cabin and septic tank,1% pipe slope, excavation works, and backfilling.
- supply material and connect waterlines from the water skid to the water tank and, from the water skid to the cabin, using 1 “price, excavation works30cm, Laying and, backfilling with appropriate soil.
SiteTawke T 12W
Completed14 November 2018