Install of 2 x sets of OPF Access Controller’s cabins and support equipment Tawke well drilling sites T12W.

  1. Prepare the ground at the designated elevation to enable the setting of the 2 sets of cabins.
  2. To cover the area prepared for the cabins with 2cm crushed gravel.
  3. block work, supply, and install concrete block under the cabin.
  4. septic tank pit excavation (2*2*2.5 m).
  5. Supplying and installing an electric water pump drawing with 1 horsepower capacity and connecting it with the main source of water and extending a wire with a socket for the electric pump and all other necessary wires that are needed. The price includes placing the electric pump in a plate box resistant to weather conditions which is to be dyed with a basic and oil-based paint.
  6. Provide and install the concrete foundation for lightning poles & installation
  7. Provide and Install Concrete Foundation for Lighting Poles, install lighting poles
  8. connect each cabin to the distribution electrical board using cable (4*4 mm^2), underground cable 50cm, and backfill with appropriate soil
  9. install spotlights and connect between the distribution of electrical board and spotlights using cable (4*4 mm^2), underground cable 50cm, and backfill with appropriate soil.
  10. supply material PVC pipe 4″ and all accessories and connect between cabin and septic tank,1% pipe slope, excavation works, and backfilling.
  11. supply material and connect waterlines from the water skid to the water tank and, from the water skid to the cabin, using 1 “price, excavation works30cm, Laying and, backfilling with appropriate soil.
SiteTawke T 12W
Completed14 November 2018