WOR-135-install of OPF combined function (accommodation and kitchen) cabin:
- disconnect the services from the existing cabin at T-12W and transport the unit to the designated DNO storage yard
- prepare the ground at the designated elevation to enable the setting of the kitchen cabin
- place the new cabin on Contractor supplied 8x 50cm square foundation blocks.
- establish an earth ground from the new cabin to an appropriate installed earth connection. (The earth electrode shall be a copper rod {3 meters in length x18mm diameter} and the earth cable shall be stranded copper conduct or swith750V grade Green/Yellow PVC insulation.)
- replace the existing power supply cable from the distribution box with Cu/XLPE/GSWA/PVC0.6/1kV10.4mm 24core cable. Underground 50cm and backfill with appropriate soil.
- inspect the existing water supply service pipe and the septic PVC disposal line. If either is mechanically damaged or charred due to ultraviolet sunlight replace it with a new tubular.
- Reconnect the water supply and septic flow lines. Underground pipes50cmandbackflill with appropriate soil.
SiteTawke T 12w
Completed18 September 2018