The sequence of the work:
- Excavation works 10 cm thickness for lean concrete,130cm or 35 cm for foundations, a total of 130cm or 45 cm excavation works in an area of 12*2.4 m.
- Sub-grade preparation by compaction and casting lean concrete 10cm, C8, 160 kg cement/m^3.
- Shuttering and steel works using 12mm bars and 16 mm bars as provided drawing, fy=410 Mpa at least.
- fixing bolts before concrete casting.
- Casting concrete C40, 450 kg cement/M^3.Take samples for tests, making slump tests.
- Using a vibration machine or mechanical vibration during casting.
- Open shuttering after 24 hours and paint with tar as waterproofing.
- Backfilling with local and clean soil. Compaction of backfilled soil to reach Proper density.
- all cutting works for plates and channel section and fixing it as provided DWG.
SiteTawke 47
Completed16 January 2019