Constructing & building concrete sub-bases for three locations outside of the Movcon office building.

The sequence of the work:

  1. Excavation Work.
  2. Supply and laying Sub-Grade.
  3. Shuttering and steel works using 12mm bars and 16 mm bars as provided drawing, fy=410 Mpa at least.
  4. Casting concrete C30.
SiteCPF –outside of Movcon office building
Completed26 August 2017