Constructing & building concrete sub-bases for three locations outside of the Movcon office building.
The sequence of the work:
- Excavation Work.
- Supply and laying Sub-Grade.
- Shuttering and steel works using 12mm bars and 16 mm bars as provided drawing, fy=410 Mpa at least.
- Casting concrete C30.
SiteCPF –outside of Movcon office building
Completed26 August 2017